15th March 2007 - Francis Road re-surfacing
Dear Resident,
We are pleased to tell you that after many years of disruption, Francis Road is going to be re-surfaced. The programme of works is as follows:
Phase 1 - Leyton High road to the Police station
* Lighting work completed.
*Footway work in progress
*Carriageway resurfacing work is scheduled for the 26th March
Phase 2-Police station to Grove Green Road
*carriageway resurfacing works scheduled for the new fianancial year{timing will be finalised when trasco complete their works}.
Whist there will be some disruption during the works ; hopefully when completethe area will look much better and safer for the long suffering residents
If you required any furtherinformation, plaese do not hesitate to contact us
Best Regards,
Councillors Chris Robbins , Anna Mbachu & Tarsem Bhogal